Oberkotzau, 8 July 2016, Katharina Thate, Organization Department

Our electricians installed 8,000 m of power cables and 5,000 m of IT cables in our new project space during the past two weeks.
Now nothing stands in the way of an optimum supply of power and IT resources! Our plumber also installed 7,000 m of underfloor heating and new water and heating lines to ensure the building remains nice and toasty.

The next step involves pouring the screed on the top floor. Then painting work can begin. Underfloor heating is still being installed on the ground floor. Afterwards, workers will pour the screed there as well. This means that everything is running according to schedule. We expect to be able to begin moving into the project space during the 37th calendar week of 2016.